Planning 5 provinces with nuclear power plants
In 2020, the first nuclear power unit in Ninh Thuan will come into operation. In the next 10 years, Vietnam will have more nuclear power plants located in Ninh Thuan, Binh Dinh, Phu Yen, Ha Tinh, Quang Ngai.
The Prime Minister has just approved the orientation of nuclear power development plan until 2030 with the goal of gradually building and developing nuclear power industry, ensuring safe management and effective exploitation of nuclear power plants. multiply and gradually increase the participation rate of domestic industries in the implementation of construction projects, advance to autonomy in design, manufacturing, construction, installation, operation and maintenance of factories. nuclear power.
The first model of nuclear power plant was built by Russia. (Photo: Tien Dung)
Accordingly, by 2015, the investment projects, locations, contractors will be completed, and project managers and key technical experts will be prepared to meet the requirements of starting construction tasks. First nuclear power machine.
It is expected that by 2020, the construction and installation of the first unit of Ninh Thuan 1 Nuclear Power Plant will be completed and put into operation, and the 2 generating sets in 2021. At the same time, start the construction of nuclear power plant. Ninh Thuan 2 and preparing the site for the construction of subsequent nuclear power plants, by 2030, will make nuclear power one of the country's main energy sources.
It is expected that in 2020 - 2030, Vietnam will master the technology of designing nuclear power plants and be able to participate in designing with foreign partners; Domestic industries involved in nuclear power plant projects with contract value accounted for 30-40% of the total construction value.
According to the development orientation, by 2020, the first nuclear power unit (capacity of 1,000 MW) will come into operation. In 2025, the total capacity of nuclear power plants is about 8,000 MW and this number increases to 15,000 MW by 2030. The rate of nuclear power accounts for 10% of the total power capacity.
The government also announced 8 locations to build nuclear power plants in Ninh Thuan, Binh Dinh, Phu Yen, Ha Tinh, Quang Ngai, each with 4-6 units built.
TT
Factory
Capacity (MW)
Operation year
1 Phuoc Dinh nuclear power unit 1
1,000
2020
2 Phuoc Dinh nuclear power unit 2
1,000
2021
3 Vinh Hai nuclear power plant unit 1
1,000
2021
4 Vinh Hai nuclear power plant unit 2
1,000
2022
5 Nuclear power Phuoc Dinh 3
1,000
2023
6 Nuclear power Phuoc Dinh 4
1,000
2024
7 Vinh Hai nuclear power unit 3
1,000
2024
8 Vinh Hai nuclear power unit 4
1,000
2025
9 Central nuclear power 1 and 2
2 x 1,000
2026
10 Central nuclear power 3
1,300 - 1,500
2027
11 Central Nuclear Power 4
1,300 - 1,500
2028
12 Central nuclear power 5
1,300 - 1,500
2029
13 Central nuclear power 6
1,300 - 1,500
2030
total capacity
15,000 - 16,000
- Potential threat from old nuclear plants
- Vietnam nuclear power needs to have standards
- The first floating nuclear power plant will operate in 2016
- Iran-Russia agreed to build 2 more nuclear power plants
- Nuclear power plant floating on water
- Germany closed all nuclear power plants by 2022
- Vietnam was back in time to build the first nuclear power
- Situation of world nuclear technology
- Russia tested floating nuclear power plant
- Method of extending the life of nuclear power plants
- Korea closed two nuclear power plants for counterfeit components
- KEPCO issues safety timetables for power plants