According to information from the Management Board of Technical Infrastructure around Ho Tay, in the third quarter of 2006, Hanoi inaugurated the wastewater collection and treatment system around West Lake.

"We try to speed up the progress to complete the installation, test run and use of waste collection and treatment station in West Lake in the third quarter of 2006 ", engineer Nguyen Dang Hung, Deputy Director Director of the Project Management Board, said. Picture 1 of Hanoi will use wastewater collection and treatment station in Ho Tay

Because it is located in the main area of ​​agricultural land and swamp area (the whole area of ​​46,037m2 belongs to Dam Bay area, Nhat Tan ward, Tay Ho district), the project to build a wastewater collection and treatment system The area around West Lake does not face many difficulties in site clearance.

However, this project has great difficulties in negotiating to buy technology lines and equipment. Under the signed contract, the plan to design the technological line for the wastewater collection and treatment station by Vatech Wabag GMBH Company (Republic of Austria) based on the comments of the scientists, Vietnam's leading experts.

In fact, to get the final opinion of Vietnamese experts, the contractor takes a lot of waiting time because of the troublesome and troublesome procedures.

The Project Management Board is "racing against time" in order to end the negotiation phase of purchasing technology and complete the construction drawing design procedures including 10,185m of main pipeline route, 5,135m of auxiliary pipeline and 7 displacement pumping stations.

"By the end of December 2005, the Project Management Board will complete construction and bidding procedures to deploy and complete construction work in May 2006. It is expected that the project will be put into trial run. and put into use in July or August 2006 ", engineer Hung hoped.

The project to build a wastewater collection and treatment system is an important item included in the Ho Tay Surrounding Technical Infrastructure Project approved by Hanoi City since 2002. The main purpose of The project is to collect and treat wastewater in the West Lake basin (where wastewater directly affects the quality of West Lake water), prevent wastewater directly affecting the lake to protect, restore and exploit. lake surface and area around West Lake.

Picture 2 of Hanoi will use wastewater collection and treatment station in Ho Tay The project has a huge investment cost, in addition to the costs for compensation and site clearance, the remaining huge amount will be spent on the construction of piping and collection systems to transfer pump stations and centralized treatment station and exhaust piping system after centralized treatment, construction of displacement pumping stations to concentrate wastewater to central treatment station, construction of concentrated waste water treatment station, capacity of 7,500 m3 / day and night in Dam Bay area, etc.

Waste water after being treated to meet standard A according to Vietnam standards on industrial wastewater is discharged into the city's common drainage system and added to the West Lake when necessary (the addition of water to the West Lake is only possible). implementing after the results of research on water quality after treatment, ensuring ecological balance of Ho Tay water