The most modern museum in Vietnam needs an additional VND 760 billion to complete

Newly put into operation (October 2010), Hanoi Museum has shown signs of degradation such as water damage, damaged exhibits, 'guests' . The museum will be invested 760 billion more to complete, increase the total investment to VND 2,800 billion.

On the afternoon of June 7, Hanoi Department of Construction and Culture said that reflecting on the projections about material degradation and water-repellent phenomenon in Hanoi Museum was real but timely remedies. Because the museum has a warranty period (24 months), some of Vinaconex's General Contractor items are responsible.

Highly appreciated for quality but still overflowing, blistering .

Head of the Hanoi Museum of Project Management Dong Huyen Ngoc said that the Hanoi Museum Museum has been completed in accordance with the required schedule and highly appreciated not only in terms of technique - art but also in quality. quality, currently in the maintenance, warranty and use stages.

Picture 1 of The most modern museum in Vietnam needs an additional VND 760 billion to complete
The black-headed bird model exhibited in the museum was bristled (Photo: Giadinh.net ).

According to Huyen Ngoc, the phenomenon of overflowing, stagnant water, blistering at the museum is related to warranty and maintenance. ' Operating time, at a toilet on the second floor, there is a leaked water valve leading to water seeping into the technical room floor in the basement 2 and making the technical box humid, ' Ngoc said.

At the same time, it was discovered that the water spill in the lift pit. In addition, at the entrance of the round core staircase, the first floor has a round space at the epoxy floor blistering, about 20cm in diameter (the total area of ​​paving floor is over 40,000m2 and nearly 600m2 of epoxy floor). ' We have collaborated with Vinaconex to find the cause and have overcome the phenomenon of overflowing, blistering at the museum ', Mr. Ngoc added.

Mr. Nguyen Van Hung - Director of Hanoi Museum - said that the specimen of black-headed bird is exhibited seriously degraded is real. ' The reason is due to the weather with high humidity, creating mold causing damage to artifacts ', Mr. Hung analyzed.

According to Mr. Hung, this was handled promptly in March 2011. The museum has collaborated with the Vietnam Museum of Forest Resources, the Soil and Agriculture Institute to check and maintain regularly for all natural objects that are kept on display at the museum.

Regarding the museum's absence, early closing, Mr. Hung said that the museum's display was not completed, so it was not attractive to visitors. However, since the inauguration date, the museum has welcomed over 600 thousand visitors.

In 2014, the museum will have enough exhibits

Deputy Director of Hanoi Department of Construction Le Van Duc said, so far the investment in Hanoi Museum is VND 2,003 billion. 'To complete the display, the museum needs an additional 760 billion dong, ' Mr. Duc said. Thus, the total investment for this project is nearly VND 2,800 billion.

Picture 2 of The most modern museum in Vietnam needs an additional VND 760 billion to complete
Some parts of the museum were overflowed but were overcome.

Museum director Nguyen Van Hung said that in the coming time, the research and collection of materials and objects will be promoted according to the requirements of the script and display design; completed two topics: 'Hanoi in the 19th century, the first half of the 20th century ' and ' Hanoi - The capital of the Democratic Republic of Vietnam ' on the National Day September 2, 2011.

The detailed design of the museum's contents has been submitted to the city leader. Representatives of the Department of Construction said that in the country, there are no qualified units to display exhibits in the museum, so this job will hire foreigners.

According to Duc, it is not until 2014 that the artifacts exhibited in the museum are fully filled. Therefore, from now until completion, the display is only temporary.